← OrreryThe Ecliptic is an Orrery publication

Cover Story · Beyond Solar desk

143 Megawatts on Paper

Four UK auction rounds have contracted about fourteen times the tidal-stream fleet the country has installed. The awards are counted after every round. What happens to them afterwards is counted nowhere.

142.76 MW
tidal stream awarded across four CfD rounds, 2022–2026, against roughly 10 MW installed in the UK today
6 MW
already terminated, in May 2026: three Orkney contracts, half of AR6's tidal awards
84.4%
of the 136.76 MW live book sits at just two sites, MeyGen and the Morlais zone
~49.6 MW
generating by 2030 in the base case, a Beyond Solar estimate

The book

Four rounds, a shrinking award, and no cheaper price.

0204060MW awarded40.82AR4 · 2022£178.54 · 85% of cap53.04AR5 · 2023£198.00 · 98% of cap28.00AR6 · 2024£172.00 · 66% of cap20.90AR7a · 2026£190.19 · 72% of capUK installed today ≈10 MWclearing price, £/MWh in 2012 money · clearing price as share of the administrative cap
Tidal stream capacity awarded in each UK CfD round with a tidal ring-fence, with the clearing price and its share of the cap. Capacities and prices from the government results documents as cited in HEL-0030; the ≈10 MW installed figure is the report's cited estimate. Not illustrative: every bar is a figure in the report.

AR4 contracted **40.82 MW** at £178.54/MWh, AR5 **53.04 MW** at £198.00, AR6 **28.00 MW** at £172.00 and AR7a **20.90 MW** at £190.19, all in 2012 money. The clearing price rose **6.5%** in real terms while the cap rose **26%**.

  • The clearing price reads budget scarcity, not cost. AR5 cleared at 98% of its cap because tidal absorbed budget floating offshore wind left unused; AR6, with no windfall, cleared 34% under.
  • A flat budget and a flat price make a smaller programme: each £m of ring-fence bought about 2.0 MW in AR4, 1.9 in AR6 and 1.4 in AR7a (Beyond Solar estimates).
  • AR8 moves tidal into a sealed ten-technology pot, capped at £371/MWh against geothermal's £219 (2024 prices), with any tidal minimum set only after bids are valued.

The attrition

An award is an option, and the options are starting to lapse.

A CfD must pass a milestone **18 months** after award. The three AR6 Orkney contracts, awarded September 2024, were terminated in **May 2026**, right on that clock. Government has just stretched the milestone to 24 months for floating wind and declined, for now, to do the same for tidal.

  • 45.32 MW of the book carries a delivery year ending by March 2027. The Morlais zone, host to 56.52 MW, now expects its first turbines in 2027, a slip of at least a year on its earliest contract.
  • MeyGen, holding 58.94 MW, closed June 2026 with £3.6m of cash; its owner calls future phases "challenging".
  • The programme publishes megawatts awarded and no equivalent for megawatts delivered, varied or terminated. The May terminations surfaced through counterparty notices, not a programme report.

The array that works

One servicing campaign can erase the margin.

0100200300400500£ per MWh generatedCfD strike, May-2026 £: AR4 265 · AR7a 282~405~127H1 2025 · 7.9 GWh~455~245H1 2026 · 4.4 GWh, one turbine ashorerevenue per MWhO&M cost per MWh
MeyGen Phase 1 revenue and operation-and-maintenance cost per MWh generated, H1 2025 and H1 2026, against the AR4 and AR7a tidal strike prices in May-2026 money. Per-MWh values and converted strike prices are Beyond Solar estimates from the company's reported generation, revenue and costs and the government's published indices, as given in HEL-0030. Not illustrative.

MeyGen's first phase earned roughly **£405–455** per MWh generated in the last two half-years under the legacy scheme. The CfD prices written for tidal's next phase are worth about **£255–293** in May-2026 money. With one turbine of four ashore, operating cost per MWh nearly **doubled**, from about £127 to £245.

  • Operation and maintenance is close to a fixed cost; energy is not. Availability, not capital cost, is the binding variable at today's servicing intervals.
  • At the H1 2026 output, O&M alone would absorb 93% of the AR4 strike price in current money; at the H1 2025 output, about 48%.
  • 43% of the live book sits at the same site, with the same servicing logistics, whose latest capacity factor was about 17% of nameplate.
  • Delivery cases for 2030: 136.76 MW if every contract is built, 77.82 MW without MeyGen's next phase, 49.56 MW in the base case (all Beyond Solar estimates).
The Ecliptic, Issue No. 011, cover analysis, drawn from Beyond Solar HEL-0030 (September 23, 2026). Awards, prices, caps, delivery years and terminations are as reported in that report's cited government and industry sources; per-MWh values, shares, MW-per-£m figures and delivery cases are Beyond Solar estimates. Neither chart is illustrative.
THE ECLIPTICan Orrery publication
Content is produced by AI systems with human editorial oversight.