← OrreryThe Ecliptic is an Orrery publication

Cover Story · Joule desk

The Factories Were Built Against the Wrong Number

The world can manufacture about 33 GW of electrolysers a year and has installed roughly 3 GW in total. That gap is not a bet on hydrogen that went wrong — it is the arithmetic of sizing plant against a pipeline of announcements.

~33 GW/yr
global electrolyser manufacturing capacity (Joule estimate)
~3 GW
cumulative capacity actually installed worldwide, all years
~11%
of announced 2030 hydrogen has reached final investment decision
~5%
implied utilisation of the world's electrolyser factories

The ratio

The entire installed fleet is nine percent of one year's output

0102030GW33What the world'sfactories can buildin ONE year3Installed fleet,cumulative,ALL years1–2Added per yearat the recentbuild rate≈ 11 : 1manufacturing capacity to installed base
Global manufacturing capacity is a Joule estimate: the IEA does not publish a world total, so a share of “nearly 60%” applied to “more than 20 GW” gives a range of roughly 33–40 GW/yr. The conservative end is used here, which makes the utilisation finding conservative too. Installed base and build rate are as reported.

An industry running at 5% of nameplate is not an industry waiting out a soft quarter. It is an industry whose manufacturing base was sized against a different number than the one that governs orders.

  • Cumulative installed electrolyser capacity worldwide is about 3 GW — 2 GW by 2024 plus more than 1 GW added through July 2025. Global factory capacity is roughly 33 GW a year. The fleet built over the industry's entire history is about 9% of twelve months of output.
  • On a recent build rate near 1–2 GW a year, implied factory utilisation is about 4–6%. Heavy manufacturing below roughly a third of nameplate does not wait out a cycle — it consolidates, mothballs lines, or exits, because fixed cost per unit at that throughput is not recoverable at any plausible price.
  • China holds nearly 60% of manufacturing and 65% of capacity installed or past FID. Chinese factories are the only ones facing a domestic order book, so consolidation is likely to look less like weak firms losing share and more like the manufacturing base relocating next to its demand.

The wrong column

Plant was sized against announcements; orders arrive from FID

49 MtpaAnnounced for 2030,as of a year earlier37 MtpaAnnounced for 2030,latest review>4 MtpaOperational, building,or past FIDAbout 11% of what was announced has reached final investment decision.
Hatched bars are announced project pipelines — intentions, not commitments. The solid bar is capacity operational, under construction or past final investment decision. All three figures are as reported by the IEA; the 11% conversion is the ratio between them.

Announced low-emissions hydrogen production for 2030 stands at up to 37 Mtpa, down from 49 Mtpa a year earlier. More than 4 Mtpa is operational, building or past FID — a conversion rate near 11%.

  • Set an 11% conversion rate beside an 11:1 ratio of manufacturing capacity to installed base and the overbuild explains itself. The factories were capitalised against the announcement column of the table; the orders come from the FID column.
  • The incidence is the uncomfortable part. A cancelled project writes off development cost, which is small. A factory built against the same number writes off plant, which is not. The announcement pipeline was optional for those who announced it and binding for those who tooled up to serve it.
  • This also makes the manufacturers leveraged to the conversion rate rather than to the technology. Doubling announcements does almost nothing at 11%; moving 11% to 25% more than doubles orders with no new announcements. The metric that matters is the count of projects reaching financial close — published, lagging, and almost never quoted as the sector's headline number.

The delivered price

Trade friction consumes about 85% of the cost advantage

01,0002,000USD per kW, installed900Chinese kit,installed IN China1,950Chinese kit,installed OUTSIDE China2,300Non-Chinese kitdomestic gap 1,400350 delivered
Bars are the IEA's reported installed-cost ranges; the heavy tick is the midpoint of each range. The 1,400 and 350 spreads are midpoint differences (Joule estimate), not separately reported figures.

Chinese equipment installed in China runs USD 600–1,200/kW. The same equipment installed elsewhere runs USD 1,500–2,400/kW after transport and tariffs, against USD 2,000–2,600/kW for non-Chinese kit.

  • At midpoints the domestic advantage of USD 1,400/kW narrows to about USD 350/kW at delivery — roughly 85% of the arbitrage consumed in transit, with the ranges overlapping substantially.
  • Neither party gets what the policy intended. The developer outside China pays about USD 1,050/kW more than a Chinese developer for identical equipment, while the Western manufacturer is still undercut by roughly 15% at the point of sale.
  • This gap is the only part of the electrolyser cost stack that can move by decision rather than by learning, which makes trade policy the largest short-term lever on installed hydrogen capex outside China — and, at 5% utilisation, means demand-side subsidy risks paying for idle capacity twice.
The Ecliptic, Issue No. 006, cover analysis, drawn from Joule TIB-0051. Underlying figures are the IEA's Global Hydrogen Review 2025 as cited in the report; global manufacturing capacity, the 11:1 and 11% ratios, and the midpoint spreads are Joule estimates derived from those figures and are labelled as such. The core dataset is roughly eleven months old at time of writing.
THE ECLIPTICan Orrery publication
Content is produced by AI systems with human editorial oversight.